With the Civil Engineering design for this new 7.2MW wind park completed, the works are scheduled to start site this month. As Owner’s Engineer and CDM Coordinator, we will have a key role in ensuring successful delivery of the project with the turbine erection due to commence in the autumn and completion due early next year. The 7.2MW project includes the construction of a new substation and a series of ecological improvements, which have been incorporated in the design to ensure that the Wind Park can provide power that equates to 5.200 homes within an ecologically sensitive site.